Data halls that hold their design conditions.

Cooling, power and monitoring designed for N+1 — and proven with an integrated systems test.

N+1
Redundancy
Precision
Cooling
IST at full load
Commissioning
DCIM / BMS
Monitoring

Data hall scope

Cooling, power and monitoring designed for N+1.

Cooling

Precision cooling sized on IT load and redundancy target.

  • N+1
  • Hot/cold aisle

UPS and power

UPS, battery and distribution systems with bypass and maintenance paths.

Containment

Containment and airflow management to reduce bypass and hot spots.

Monitoring

Environmental and power monitoring integrated with DCIM or BMS.

Fire suppression

Gas suppression and early-warning detection to local code.

IST

Integrated systems test at full load before the hall is handed over.

Delivery sequence

  1. 01
    Requirement

    IT load, redundancy and future growth agreed with the operator.

  2. 02
    Design

    Cooling, power and containment laid out around the rack plan.

  3. 03
    Construction

    Installation with leak, load and failover testing.

  4. 04
    IST

    Integrated systems test at full load, witnessed and recorded.

Discuss a data hall fit-out